Kostnad och ytvärdering vid byggnadsekonomiska jämförelser
KTH, Superseded Departments, Civil and Architectural Engineering.
1964 (Swedish)Report (Other academic)Alternative title
Cost and area valuing in building economical comparisons (English)
Abstract [en]

In this article certain economical questions concerning the choice of design of building parts (outer-walls, inner-walls, staircases etc.) are discussed. Primarily the dimensions of building parts as a function-of-the-profitable area are studied.

The author has in his economical calculations tried to differentiate strictly between cost and value. This has been considered a basic condition for correct comparative economical analyses. Cost can be characterized as a sacrifice expressed in money for the production and sales of a product including normal profit. The value of the product can on the other hand be regarded as a subjective amount depending in addition to these costs on who the valuer is.

The design of the building part can amongst other things be studied from the point of view of the area which it covers. By giving this area a value it is possible to make economical dimensioning calculations.

If it is assumed that the floor-area is constant (fixed outerdimensions)the area value can have direct significance on the choice of the design of a building part. For example if the saved area can be valued highly it can be economically defensible to choose constructions which take up a small area even if these relatively mean higher costs.

The size of the area value will depend on the assumptions fundamental to the valuing. The following two methods of valuing have been analysed more deeply, namely, each usable square meter is given in principle the same value in the house and each additional usable square meter is valued in relation to its cost (marginal-cost).

In the first case mentioned with the constant value per area it is easy to over-value the area won(choice of less space-craving constructions) in relation to its cost.The disadvantage with overvaluing can be avoided if one instead values in relation to the marginal-costs for the extra area.

The area value will on the other hand lose all significance if the size of the usable area is determined in the planning work. The result will be that in the choice of the design one can concentrate entirely on analysing the dimensions which require a minimum of costs. This can in its turn mean that one will choose more space-craving but less moneycraving constructions.

Place, publisher, year, edition, pages
Meddelande. Inst. för byggnadsteknik, ISSN 0346-5918 ; 38
Keyword [sv]
National Category
Building Technologies
URN: urn:nbn:se:kth:diva-34560OAI: diva2:422863
QC 20110616Available from: 2011-06-16 Created: 2011-06-10 Last updated: 2011-06-16Bibliographically approved

Open Access in DiVA

fulltext(3422 kB)87 downloads
File information
File name FULLTEXT01.pdfFile size 3422 kBChecksum SHA-512
Type fulltextMimetype application/pdf

By organisation
Civil and Architectural Engineering
Building Technologies

Search outside of DiVA

GoogleGoogle Scholar
Total: 87 downloads
The number of downloads is the sum of all downloads of full texts. It may include eg previous versions that are now no longer available

Total: 43 hits
ReferencesLink to record
Permanent link

Direct link