Orsaker till förseningar i byggbranschen
KTH, School of Architecture and the Built Environment (ABE), Civil and Architectural Engineering, Building Technology and Design.
KTH, School of Architecture and the Built Environment (ABE), Civil and Architectural Engineering, Building Technology and Design.
2012 (Swedish)Independent thesis Basic level (professional degree), 10 credits / 15 HE creditsStudent thesisAlternative title
Causes of delays in the construction industry (English)
Abstract [sv]

Med anledning av JM:s satsning på Lean Construction, där företaget arbetar med att effektivisera verksamheten, syftar detta arbete till att identifiera frekvent försenade arbetsmoment och orsaker till detta. Arbetets datainsamling av olika typer av förseningar har avgränsats till nio tillhandahållna flerbostadsprojekt från olika delar av Sverige. Den data som har behandlats innefattar mötesprotokoll och tidsplaner som sedan låg till grund för de personliga intervjuer med arbetsledning för de olika projekten. Utifrån insamlad data och intervjuer genomfördes en enkätundersökning via Internet riktad till arbetschefer, platschefer och arbetsledare. Totalt blev 93 stycken personer från Stockholm och 95 från regioner inom affärsenheten Riks blev inbjudna att delta i undersökningen. 

Genom granskning av tillgängligt material kunde det konstateras att de arbetsmoment som vanligen upplever någon form av försening är:

Arbeten under normalplan

  • Ställningsarbeten
  • Fasadarbeten
  • Hissmontage
  • Plattsättning
  • Köksleveranser

Vad beträffar arbeten under normalplan är brisfälliga geotekniska undersökningar en vanlig orsak till försening, vilket i sin tur kan leda till undermåliga bygghandlingar.  Andra vanliga orsakerna till att ovanstående moment blir försenade är framförallt bristande styrning av egen personal och underentreprenörer. Detta gäller i både upphandling som i det dagliga arbetet. Vid upphandling förekommer det otydligheter angående arbetets omfattning samt när och hur det ska utföras. Detta gäller främst vid avtal med dotterbolag. I det dagliga arbetet uppstår problem med styrning framförallt på grund av otydligheter i kommunikationen. Personalen är inte alltid medveten om hur och när arbetet skall utföras. Detta förvärras även ytterligare av att arbetsledningen i olika projekt har olika planeringsrutiner och ställer olika höga krav.

JM måste bli bättre på att genomföra mer utförliga geotekniska undersökningar. Detta för att undvika de annars stora risker för felaktiga handlingar som sedan kan orsakar förseningar och merkostnader när projekt stöter på icke förutsedda problem.

Företaget måste även bli bättre på rutiner kring styrning och planering av arbete. Det är därför viktigt att tydliga avtal upprättas med underentreprenör, där samtliga parter är delaktiga i planeringsprocessen. För att förbättra arbetet med Lean är det även viktigt att JM blir bättre på att dokumentera förseningar och orsaker till dessa. Utöver detta bör det även skapas ett särskilt system som kan hantera och bearbeta avvikelser gentemot tidsplanen. 

Abstract [en]

Following JM's focus on Lean Construction, where the company is working to streamline its operations, this report aims to identify frequently delayed operations and the reasons for this. The data collection of different types of delays has been limited to nine provided apartment building projects from different parts of Sweden. The processed data includes meeting minutes and schedules which then formed the basis of personal interviews with supervisors of the various projects. Based on the collected data and interviews a survey was conducted on the Internet targeted at managers, site managers and supervisors. A total of 93 people from Stockholm and 95 from regions within the National Business Unit were invited to participate in the survey.

Through review of available material, it was found that the operations that usually experience some form of delay are:

• Works below ground level

• Scaffolding

• Cladding

• Elevator montage

• Tiling

• Delivery of kitchen fittings

As for work below ground level the substandard geotechnical studies are a common cause of delay, which in turn can lead to substandard construction documents. Other common reasons for the delays in the aforementioned operations are above all a lack of managing of their own personnel and subcontractors. This applies both in the case procurement as well as their daily work. In the procurement of subcontractors, there is often ambiguity regarding the extent of the work and when and how to execute the work. This applies especially to the agreements with affiliates. In everyday operations problems with managing caused by ambiguity in communication often appear. Staff is not always aware of how and when the work is to be performed. This is exacerbated even further by the site management in different projects that have different planning processes and have different demands.

JM needs to implement more detailed geotechnical investigations. This is to avoid the otherwise high risk of substandard construction documents which then can cause delays and additional costs when the project encounters unforeseen problems.

The company must also be better at tasks involving planning and managing work. It is therefore important that clear agreements are established with the subcontractor, in which all partners are involved in the planning process. In order to improve the work with Lean, it is also important that JM gets better at documenting delays and their causes. In addition, they also need to create a special system that can manage and process deviations from the schedule.

Place, publisher, year, edition, pages
2012. , 49 p.
Keyword [en]
delays, causes, Lean Construction, Structured Production, scheduling
Keyword [sv]
förseningar, orsaker, Lean Construction, Strukturerad Produktion, tidsplanering
National Category
Civil Engineering
Identifiers
URN: urn:nbn:se:kth:diva-102027OAI: oai:DiVA.org:kth-102027DiVA: diva2:550360
External cooperation
JM AB
Subject / course
Constructional Engineering and Design
Educational program
Bachelor of Science in Engineering - Constructional Engineering and Design
Uppsok
Technology
Supervisors
Examiners
Available from: 2012-09-10 Created: 2012-09-06 Last updated: 2013-03-07Bibliographically approved

Open Access in DiVA

fulltext(3682 kB)718 downloads
File information
File name FULLTEXT01.pdfFile size 3682 kBChecksum SHA-512
0c19f7b3dd26910c8b116086a2f1238419f616e537ffe0f457df6552ea35758084faedc75a1d1184085d4f67a6d896f8bccb4989d53af46d8e15a55712e7623b
Type fulltextMimetype application/pdf

By organisation
Building Technology and Design
Civil Engineering

Search outside of DiVA

GoogleGoogle Scholar
Total: 718 downloads
The number of downloads is the sum of all downloads of full texts. It may include eg previous versions that are now no longer available

urn-nbn

Altmetric score

urn-nbn
Total: 955 hits
CiteExportLink to record
Permanent link

Direct link
Cite
Citation style
  • apa
  • harvard1
  • ieee
  • modern-language-association-8th-edition
  • vancouver
  • Other style
More styles
Language
  • de-DE
  • en-GB
  • en-US
  • fi-FI
  • nn-NO
  • nn-NB
  • sv-SE
  • Other locale
More languages
Output format
  • html
  • text
  • asciidoc
  • rtf