Suitable analysis methods are needed for evaluation of future timetable scenarios, both in short term operational planning and for strategic planning with a longer time horizon. One method is to use simulation software which makes it possible to model large networks. The Swedish Transport Administration (Trafikverket) is in a process where the aim is to start using simulation software RailSys as a tool for timetable planning. This will at first be applied for long term strategic planning with the possibility to also use it in operational planning further on.
The main focus in this paper is to estimate primary run time extensions from registered data. Ideally these should only represent primary causes, e.g. decreased vehicle performance, variation in driver behaviour or infrastructure malfunctions. These extensions are important in order to make simulations more realistic.
Different reduction levels of registered data are tested in order to estimate primary run time extensions. Registered data used are absolute values without distinction between primary and secondary causes. Calibration simulations are done on the Southern main line in Sweden where the mix of high and low speed trains is substantial.
Keywords
railway operation, simulation, train delay
National Category
Transport Systems and Logistics
Research subject
Järnvägsgruppen - Kapacitet
Identifiers
urn:nbn:se:kth:diva-76754 (URN)
Conference
Railway Engineering 2011. London, UK. 28th June 2011 - 30th June 2011
Note
TSC import 863 2012-02-06. QC 20120413
2012-02-062012-02-062022-06-24Bibliographically approved