Trafikverket (the Swedish Transport Administration) is the single largest purchaser of construction work and therefore concerned with the development of their procurement process. As a step in the right direction the enquiry basis will be designed in alignment to the demand of a more lucid risk distribution for entrepreneurs, with the intention to reflect the client’s intentions. The goal is to create a market situation that will spawn an increased social benefit by way of "more roads for the money".
The purpose of this Thesis is to make a follow-up of the procurement process in accordance with the building of the new traffic solution E18 Hjulsta-Kista. Focused on identifying how bidders in different projects experience The Swedish Transport Administrations procurement process, thus elucidating possible improvements of the processes.
The research was interview based and the questions were designed to give a detailed as well as a general picture of the data gained through a analysis of the survey with diagrams.
The study points out that through the availability of calculated quantities more accurate pricing offers will be given to Trafikverket. Procurement process efficiency can be achieved through a transparent bid opening at the evaluation face. It is also agreed upon that no deviation from the trade regulatory framework is allowed.