Tillvalsprocessen: EN STUDIE AV EN MINDRE BYGGENTREPRENÖRS ARBETE MED TILLVAL VID NYPRODUKTION AV BOSTADSRÄTTER
2011 (Swedish)Independent thesis Advanced level (degree of Master (Two Years)), 20 credits / 30 HE credits
Student thesisAlternative title
The option process : A STUDY OF A SMALL CONSTRUCTION CONTRACTORS WORK WITH OPTIONS IN CONSTRUCTIONS OF NEW CONDOMINIUMS (English)
Abstract [sv]
Tillval är de val bostadsrättsköparen gör som inte ingår i standardutförandet för den
nyproducerade bostad som hon eller han har bokat. Tillval är inom nyproduktion av bostadsrätter
en viktig faktor för att locka och binda köpare till det aktuella projektet. Hanteringen av tillvalen
inom ett projekt kallas tillvalsprocessen. Tillvalsprocessens utformning är en avvägning mellan
produktionens önskan på förutsägbarhet och kundens önskan på flexibilitet.
Tillvalsprocessen blir inte bara omfattande inom själva produktionen men också inom
administrationen och hantering av dem samma.
Byggnadsfirman Viktor Hanson AB bygger i skrivande stund sina första bostadsrätter i egen
regi. Företaget har i och med detta blivit tvungen att utforma en tillvalsprocess. Detta
examensarbete är en del i företagets strävan att utveckla och förbättra sin egen verksamhet.
Syftet är att utreda hur den tillvalsprocess som Viktor Hansson byggt upp beskrivs och
uppfattningarna om processen bland dem som arbetar i processen för att hitta möjliga
förbättringsåtgärder.
Frågeställningen som har ställts är följande:
På vilka punkter kan Viktor Hanson effektivisera sin tillvalsprocess?
För att kunna svara på denna fråga har projektet Annedalsterrassen i Annedal utanför Stockholm
studerats. Detta har gjorts genom en fallstudie av projektets tillvalsprocess. Undersökningen har
baserats på djupintervjuer med medarbetare inom tillvalsprocessen.
Den teoretiska grunden för analysen av intervjuerna baseras på intressentteori och ANT: Aktörnätverksteori.
Analysen av det empiriska materialet har skett i tre steg, först en textanalys för att
hitta mönster och nyckelbegrepp. Sedan en visualisering av hela tillvalsprocessen genom att
utifrån respondenterna syn av tillvalsprocessen beskriva en generell bild av processen och dess
olika delmoment. Sist gjordes en jämförande analys där det empiriska materialet jämfördes med
den teoretiska grunden.
Resultaten av studien och svaret på frågeställningen sammanfattas i fem punkter.
Tid – Försök skapa mer tid för tillvalsprocessen
Rollfördelning – Få in tillvalshanteraren tidigare i processen.
Arbetsformer – Se till att dokumentera hur arbetsprocesser genomförs .
Kvalitetssäkring – Utveckla en databas för tillvalsavtalen.
Tydlighet – Tillse att all information till kunderna är korrekt och att alla vet vad som
gäller.
Abstract [en]
Options are the choices a condominium buyer has chosen that is not included in the standard
design for the newly constructed home that she or he has chosen. Options are an important factor
in the construction of new condominiums to attract and keep customers to the project. The
management of the options in a project called the option process. The option process design is a
balance between construction management’s desire for predictability and the customer's desire
for flexibility.
Options process will not only be comprehensive in the construction itself, but also in
administration and management of them the same.
Byggnadsfirman Victor Hanson AB is in the time of this writing constructing their first
condominiums of their own. The company has there for been forced to develop an option
process. This thesis is a part of the company's efforts to develop and improve their
operations. The purpose of this study is to investigate how the option process that Victor Hanson
has built up is described by those involved in the process.
The question of framing is therefore as follows:
How could Victor Hanson make its option process more effective?
To answer this question, the project Annedalsterrassen in Annedal outside Stockholm has been
studied. This has been done through a case study of the projects option process. The study is
based on interviews with employees in the option process.
The theoretical basis for the analysis of the interviews based on stakeholder theory and ANT:
Actor-network theory. The analysis of the empirical material has taken place in three stages, first
a text analysis to find patterns and key concepts. Then a visualization of the entire option process
by evaluate the respondents view of the option process and describe a general picture of the
process and its various components. Lastly a comparative analysis were the empirical data was
compared with the theoretical foundation.
The results of the study and the answer to that question of framing are summarized in five points.
• Time - Try to create more time for option process
• Role management - Involve the option manager earlier in the option process.
• Forms – Make sure to document how work processes are done.
• Quality Assurance - Develop a database of contracting.
• Clarity - Ensure that all customer information is correct and that all involved are informed
Place, publisher, year, edition, pages
2011.
Series
Examensarbete INDEK ; 2011:27
National Category
Engineering and Technology
Identifiers
URN: urn:nbn:se:kth:diva-91087OAI: oai:DiVA.org:kth-91087DiVA, id: diva2:508129
Educational program
Master of Science in Engineering - Urban Management
Uppsok
Technology
Supervisors
Examiners
2012-03-072012-03-072022-06-24Bibliographically approved